1st level bearing walls
Framing 1st living level bearing walls.
Framing Update
The pool is ready to be backfilled and the framers are just about finished wth the 1st living level exterior walls.
Pool Shell
Pool Shell
Pool Shell
Today Oasis Custom Pools is completing the unique process of "Shooting Gunite" to form the hard concrete shell of the pool. Gunite is a...
Framing
Framers are building walls on the ground level and installing the decking for the 1st floor.
Pool Update
Waiting for Pool inspections and then we will shoot the pool shell next week.
1st Level Floor Trusses
Site has been cleaned up and Framers are installing the 1st level floor trusses.
Tie Beams Complete!
Now that the tie beam is poured, we will spend the next couple of days cleaning up the lot. The floor trusses will be delivered next week...
Tie Beams
Tie beams are up
Block Walls
Mason's are onsite.